DC Court of Appeals Ruling Against FERC: Process, Not Substance
June 8, 2014 § Leave a comment
Much ado being made in the press by environmental groups about a “big win” from the DC Court of Appeals related to a Tennessee Gas pipeline project, but at the end of the day it’s purely about process and not substance. The $500 million project was complete long before the ruling came down, and gas continues to flow through the pipeline to the high demand markets in the Northeast.
So what’s all the chatter about?
On Friday, June 6, 2014, the DC Circuit Court of Appeals found deficiencies in the process that the US Federal Energy Regulatory Commission (FERC) used for its environmental assessment (EA) of Tennessee Gas Pipeline’s Northeast Project. The ruling was based on the FERC considering individual upgrade projects separately rather than assessing the cumulative environmental impact.
The Court found that FERC impermissibly segmented the environmental review in violation of the National Environmental Policy Act (NEPA) and remanded the case back to the FERC for further consideration. Commission attorneys had argued that its 200-page environmental assessment of the 40-mile section of pipeline through New Jersey called the “Northeast Upgrade” project analyzed all of the pipeline’s cumulative impacts.
Make no mistake, the Court did not find that the project, even taken as a whole, had impermissibly impacted the environment. The ruling was purely based on the process used by the FERC, and not on the merits of this pipeline project or any future projects.
Kinder Morgan issued a statement that,”[w]hether the completed expansion projects are considered individually, as FERC did, or cumulatively, we do not expect any change in the ultimate conclusion that there was no significant environmental impact resulting from the projects.”
Background
The FERC completed an environmental assessment in November 2011 t and issued its recommendation of a finding of no significant impact. In May 2012, FERC issued a certificate of public convenience and necessity to Tennessee for the Northeast Project, authorizing construction of five pipeline loop segments totaling more than 40 miles of 30-inch-diameter pipe in Pennsylvania and New Jersey. The project also included adding 22,310 horsepower of compression at two existing compressor stations in Pennsylvania.The project was placed into service in November, adding 636,000 Dt/d of capacity to Tennessee’s 300 Line System.The Delaware Riverkeeper Network, New Jersey Highlands Coalition and Sierra Club’s New Jersey chapter petitioned the court to review FERC’s order approving the project.
The Legal Tussle
The Delaware Riverkeeper Network, the New Jersey Highlands Coalition and the New Jersey Sierra Club argued the decision-making process did not take into account other natural-gas expansion projects seeking approval at the same time in New Jersey.
FERC argued that each project was a stand-alone project that would provide gas to different customers during different time frames.
The Court ruled that given the interrelatedness of the projects as well as their temporal overlap, the FERC was obliged to consider the other three Tennessee Gas pipeline projects when it conducted its NEPA review of the Northeast Project. The Court also held that the NEPA review of the Northeast Project violated the segmentation rule, which was upheld by the Supreme Court in 1976, as an agency is prohibited from dividing “connected, cumulative, or similar federal actions into separate projects and thereby [failing] to address the true scope and impact of the activities that should be under consideration.”
What the Ruling Did Not Say
Make no mistake, the Court did not reach a finding that the project, even taken as a whole, had impermissibly impacted the environment. The ruling was purely based on the process used by the FERC, and not on the merits of this pipeline project or any future projects.
Kinder Morgan issued a statement that,”[w]hether the completed expansion projects are considered individually, as FERC did, or cumulatively, we do not expect any change in the ultimate conclusion that there was no significant environmental impact resulting from the projects.”
So Now What?
Business as usual. Make no mistake; gas will continue to flow through the pipeline regardless of this ruling. FERC will consider the project as a whole, and ultimately, their assessment of environmental impact may not change. Environmental groups are pushing for the imposition of new requirements to mitigate impacts, but that will not happen without a finding requiring such measures.
What will change as a result of this ruling is the NEPA submissions in advance of new projects will be required to include related projects and cumulative impact studies—not a difficult task given the considerable work performed to comply with NEPA before every pipeline project. Ultimately this ruling is about process and not a significant substantive change.